Anticipated Permits and Authorizations

The following permits and other authorizations are anticipated to be required in connection with potential decisions reached following preparation of the Plan-EIS:

  • Clean Water Act Permits. Implementation of this project may require a permit and/or supporting certification under Sections 401, 402 and 404 of the Clean Water Act.

  • Hood River County Permits. A permit may be needed and authorization regarding land use compatibility.

  • Oregon Department of State Lands Permits. Implementation of this project may require permits associated with working in waters of the State.

  • Oregon Department of Geology and Mineral Industries Permit. A permit may be required for areas lacking an existing permit.

  • Consultation. Consultation will be completed with the Oregon State Historic Preservation Office, National Marine Fisheries Service, and U.S. Fish and Wildlife Service.